2.11 In November 2000, the Agency generated market awareness by hosting an industry conference that attracted over 250 delegates from about 100 companies. The delegates learnt that completion of the bid documents and publication of a notice in the Official Journal of the European Communities (OJEC), inviting potential bidders to express their interest in the project, were scheduled for summer 2001. The Agency also stated that it planned to award the contract in autumn 2002 (Appendix 5).
2.12 The Agency published the OJEC notice in August 2001. By October, nine consortia, representing 21 companies (contractors and investors), had responded to the Agency's pre-qualification questionnaire. The questionnaire requested the sort of standard information that clients seek about potential bidders, including financial status, technical capacity and experience. The Agency judged that six responses had passed the qualification standards, with the scores from five being, for all intents and purposes, identical (Figure 10). It, however, did not produce a short list because it was taking longer than expected to produce its bid documents.
2.13 In mid 2002, the Agency became aware that some of the potential bidders had started to doubt the Agency's commitment to the project. If the Agency had had a better understanding of the time required for preparing its bid documents, it could have delayed publication of the original OJEC notice. In so doing, it would have reduced the risk of wavering bidder interest.
9 | Coverage of the Base Case and High demand scenarios |
|
|
|
| |||
|
|
|
| Included work |
|
|
| |
| Two year | Operation and | Committed | Uncommitted |
| Maintaining |
| |
Demand Scenario |
|
|
|
|
|
|
| |
Base Case |
|
|
|
|
|
|
| |
High |
|
|
|
|
|
|
| |
Payment Mechanism |
|
|
| |||||
Source: National Audit Office |
|
| ||||||
10 | The Agency received six satisfactory responses to its 2001 pre-qualification questionnaire |
Consortium | Members | The Agency's scoring of |
GeneSYS | Fluor & Mott Macdonald | 81.78 |
Highway Communications | Thales Translink, Haliburton, Mouchel, Siemens Traffic Controls Ltd | 81.17 |
Roadside Telecommunications Group | Marconi Communications Ltd, Serco Ltd | 81.07 |
Atkom | WS Atkins Investments Ltd, Charterhouse Project Equity Investments Ltd, Cable & Wireless UK Services Ltd | 79.80 |
BT/AMEC | BT, AMEC | 79.58 |
LINK | Pell Frischmann Consultants Ltd, Thus, Royal Bank of Scotland plc, Morrison Construction Ltd | 65.69 |
Balfour Beatty Power Networks | Balfour Beatty Power Networks, Thus | Submission did not |
Morricom Ltd | Morricom Ltd, Optic Trunks Ltd | Submission did not |
Jasmin | Jasmin | Submission did not |
Source: The Highways Agency |
|
|
2.14 Concerned that some of the bidders were losing interest in the project, the Agency took the unusual step of reissuing the advert in the OJEC in August 2002. While the responses demonstrated continued market interest, with the Agency again receiving nine expressions of interest (Figure 11), two of the higher scoring potential bidders (Highway Communications and Atkom) did not respond. Only four interested potential bidders passed the Agency's qualification standards. All four were short listed to proceed further.