While the case for the NRTS remained positive, the rationale for using the PPP procurement route became more limited

2.26  When opportunities for commercial exploitation of the up-graded infrastructure fell away, the Agency reviewed whether a PPP was the most appropriate procurement route. The Agency's investment decision for a PPP came to rest on:

  creating a long-term relationship with a single contractor that had borrowed money to upgrade the systems and was better placed than the Agency to manage the risks involved;

  paying for services when they are delivered; and

  a cost comparison that showed that the PPP was no more expensive than conventional procurement.

14

GeneSYS's bid fell by £2 million during the preferred bidder stage

 

 

 

Break down of GeneSyS's bid at award of contract

£ millions
(2004 prices)

Unitary charges

242

 

 

Connection maintenance charges

16

 

 

Charges for called off additional works

126

 

 

 

 

384

 

Break down of GeneSyS's Revise and Confirm bid

 

 

 

Unitary charges

253

 

 

Connection maintenance charges

27

 

 

Charges for called off additional works

131

 

 

Differences between the bids

 

 

 

Removal of the Camera Mast Service

(20)

 

 

Cumulative changes to the demand scenarios

(5)

 

 

 

 

386

 

 

 

(2)

 

Cost of changes in responsibilities between Revise and Confirm bid and contract award

 

 

 

GeneSYS's acceptance of responsibility for duct chambers in structures and cross carriageway ducts

6

 

 

Confirmation that responsibility for designated links remains with the Agency

(6)

 

 

GeneSYS's acceptance of responsibility for delays to called off additional works caused by other Agency employed contractors

4

 

 

Other changes in responsibilities

6

 

 

 

 

10

 

Cost changes between Revise and Confirm bid and contract award

 

 

 

Base price date moved from April 2004 to December 2004

(6)

 

 

Interest rate lower than assumed in the Revise and Confirm bid

(5)

 

 

Sum of other cost increases

7

 

 

Sum of other cost decreases

(8)

 

 

 

 

(12)

 

 

 

(2)

 

Source: Highways Agency