3.26 To date, progress of construction activities has met expectations, with key milestones along the route attained as follows:
■ all civil engineering works at Ebbsfleet and in the Thames Valley are now complete including the 1km viaduct structure at Thurrock and the installation of piled slab-work across the Rainham Marshes. The route was handed over to the track-work and signalling contractors on schedule. The shell of the new international station at Ebbsfleet is complete;
■ all tunnelling along the Section 2 route is complete with over 20km of twin bored tunnels completed on or ahead of programme;
■ a 1km long and 50m wide reinforced concrete box housing station platforms has been constructed below ground level at Stratford and the shell of the new international station building is complete;
|
18 |
The higher the cap on overrun sharing arrangements, the longer the project manager's interest in finding cost reduction measures is preserved. |
||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bands for sharing cost overrun
|
1 Project Manager will not benefit from finding cost reduction measures and so rationally will not seek them out. |
||||||||||
|
|
|||||||||||
|
|
|||||||||||
■ works in the King's Cross Lands are well-advanced. Major bridges across the East Coast Main Line and the Midland Main Line were slid into place on programme;
■ the St Pancras Interim Station was opened on schedule in April 2004 allowing works to build a new underground Thameslink station to commence on schedule in September 2004. The scheduled works were completed within the programmed 34-week suspension of the Thameslink service;
■ work on the Grade I listed Barlow Shed at St. Pancras is underway. The work has proved to be difficult but solutions to the technical issues have been identified; and
■ Trackwork is well advanced and signalling installation has commenced.
3.27 The Department and LCR expect that the final cost of Section 2 will exceed the target cost. LCR attributes most of the increase to the effect of railway-related inflation being greater than that assumed in 2001 at the outset of the Section 2 project. Once inflation is removed, LCR expects that the cost of Section 2 will be within a few percentage points of the target. For the taxpayer, the cost overrun on Section 2 that is not absorbed by the Cost Overrun Protection Programme would, under current arrangements, ultimately flow through to amounts drawn down under the access charge loan facility.