All parties contributed to the Composite Solution in different ways and degrees

Assembling the Composite Solution required consistent progress to be made on five parallel fronts, each of which were major projects in their own right. The projects were:

  A cost reduction initiative within NATS;

  Implementation of the interim solution, a temporary working capital facility;

  Identification and selection of a new corporate shareholder;

  Extensive revisions to NATS' three major bank facilities for the Company's acquisition, working capital and capital investment; and

  Negotiations between NATS and the Civil Aviation Authority following NATS' request for the relaxation of the caps on its prices and other changes in the regulatory framework.