Financial
Risk No. | Financial | Risk Description | Consequences of Risk | Assessment of Risk | Risk Score | Owner | Action Plan | Target Date | |
Probability | Impact |
|
| ||||||
F1 |
| Underestimate the level of required project resourcing and funding required to successfully deliver the project | Inadequate budgets are identified Stability of the programme and project teams is undermined. | 2 | 3 | 6 | Report Risk within the monthly Highlight Report. Monitor Budget via trigger points in Highlight Report Check previous project budgets or evaluate costs / resourcing of similar projects in other authorities |
| |
F2 |
| The costs of project implementation outweighs the benefits. | Best and final bid fails affordability check and project is deemed uneconomic. | 1 | 3 | 3 | The Business Case and requirements will be reviewed. |
| |
F3 |
| No bids received which meet the Affordability Model | Failed procurement if not supported by market interest | 3 | 3 | 9 | Soft market testing pre-advertisement. Review other LAs engaged in partnerships |
| |
F4 |
| Uncertainty over how to apportion financial savings that arise from process re-engineering. | Problems encountered in achieving process efficiencies and lack of ability to manage the required level and commitment across the organisations. De-stabilise the relationship and delivery plans | 2 | 2 | 4 | Ensure allocation is clear in benefits realisation plan and contract documentation |
| |