ISDS evaluation scores
Corporate and Transactional Services Procurement Pack - ISDS evaluation framework
Weight | Bidder 1 - Std | Bidder 1- VB1 | Bidder 1 - VB2 | Bidder 2 - Std | Bidder 2 - VB1 | Bidder 2 - VB2 | Bidder 3 - Std | Bidder 3 - VB1 | Bidder 3 - VB2 | ||||||||||||||||||||||
% | Raw score | Weighted score | Raw score | Weighted score | Raw score | Weighted score | Raw score | Weighted score | Raw score | Weighted score | Raw score | Weighted score | Raw score | Weighted score | Raw score | Weighted score | Raw score | Weighted score | |||||||||||||
5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | |||||||||||||
5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | |||||||||||||
5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | |||||||||||||
5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | |||||||||||||
5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | |||||||||||||
3.00% | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | |||||||||||||
3.00% | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | |||||||||||||
3.00% | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | |||||||||||||
3.00% | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | |||||||||||||
3.00% | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | 10 | 3.00 | |||||||||||||
2.00% | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | |||||||||||||
2.00% | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | |||||||||||||
2.00% | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | |||||||||||||
2.00% | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | |||||||||||||
2.00% | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | |||||||||||||
2.00% | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | |||||||||||||
2.00% | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | |||||||||||||
2.00% | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | |||||||||||||
2.00% | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | |||||||||||||
2.00% | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | 10 | 2.00 | |||||||||||||
Total for Service Delivery and Technical | 60.00% | 60.00 | 60.00 | 60.00 | 60.00 | 60.00 | 60.00 | 60.00 | 60.00 | 60.00 | |||||||||||||||||||||
Financial and Commercial | |||||||||||||||||||||||||||||||
Overall Costs, Affordability and Value for Money | 5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | ||||||||||||
Financial and Economic Standing of the Consortia | 5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | ||||||||||||
Financial Robustness of the Bid | 5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | ||||||||||||
Deliverability of the Funding Package | 5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | ||||||||||||
Total for Financial and Commercial | 20.00% | 20.00 | 20.00 | 20.00 | 20.00 | 20.00 | 20.00 | 20.00 | 20.00 | 20.00 | |||||||||||||||||||||
Legal and Contractual | |||||||||||||||||||||||||||||||
Extent to which Bid meets the Local Authority's expectations | 5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | ||||||||||||
Commercial Robustness | 5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | ||||||||||||
Ability to support the Model Contract | 5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | ||||||||||||
Total for Legal and Contractual | 15.00% | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | 15.00 | |||||||||||||||||||||
Overall Integrity and Best Value | |||||||||||||||||||||||||||||||
Consistency of technical, financial and legal proposals | 5.00% | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | 10 | 5.00 | ||||||||||||
Total for Overall Integrity and Best Value | 5.00% | 5.00 | 5.00 | 5.00 | 5.00 | 5.00 | 5.00 | 5.00 | 5.00 | 5.00 | |||||||||||||||||||||
Total Score for Bid | 100.00% | 100.00 | 100.00 | 100.00 | 100.00 | 100.00 | 100.00 | 100.00 | 100.00 | 100.00 | |||||||||||||||||||||
Notes | Instructions |
Std = standard bid | 1. Agree weighting of main criteria (Service & Delivery, Financial and Commercial, Legal and Contractual, Overall Integrity and Best Value) |
VB1 = variant bid 1 | 2. Agree weighting of sub-criteria (e.g. method statement 1) |
VB2 = variant bid 2 | 3. Score each sub-criteria out of 10 (see scoring criteria overleaf) |