5.I - Substantial pre-ATP milestone payments and/or significant scalability risk
Discussion | |
The baseline MISMA drafting assumes that there is little risk in making non-recoverable milestone payments on the basis that: a) Transformation (and hence transformed service delivery) is not high risk. b) Costs of transformation are not substantial. c) There may only need to be a single milestone payment (at ATP). d) Roll-out of transformed services is neither prolonged nor involves significant scalability risk. Where there is significant variance from one or more of the above, introduction of provisions relating to a Contract Performance Point (which provides protection against scalability risk by making milestone payments recoverable in the event of termination for under/non-performance) should be considered. | |
Provisions to consider | |
Provision and reference | Considerations |
Contract Performance Point References: Model Agreement Clause 55.5.2. Clause 58.6. Schedule 7.1, Section C, Part A, para 4.4. | The Contract Performance Point (CPP) provisions allow for a CPP to be set at some point after the completion of transformation which, through pre-agreed tests, demonstrates that the Services are performing satisfactorily at full scale operation. Should the Authority have to terminate for Contractor default prior to CPP, the CPP-related provisions then allow them to recover some or all of any milestones designated as potentially recoverable in the contract. Keeping this claw-back right linked only to a termination event should remove any revenue recognition concerns and for this reason, although the CPP provisions add commercial complexity to MISMA, they should not significantly prolong negotiations. |