(a) If the Proponent discovers any ambiguity, discrepancy or inconsistency between any of the provisions of this Agreement or any other document expressly incorporated into this Agreement:
(1) it must notify the Project Owner of this in writing; and
(2) the Project Owner will direct the Proponent as to the interpretation to be followed by the Proponent in performing its obligations under this Agreement.
(b) If the Project Owner discovers any ambiguity, discrepancy or inconsistency between any of the provisions of this Agreement or any other document expressly incorporated into this Agreement, the Project Owner will direct the Proponent as to the interpretation to be followed by the Proponent in performing its obligations under this Agreement.
(c) The Proponent is not entitled to any additional costs by reason of a direction from the Project Owner under this clause 1.4.