7.1  Development of Project Proposal

(a)  The Project Proposal must be developed by the Proponent in accordance with this clause 7.

(b)  In developing the Project Proposal, the Proponent must have regard to the requirements of the Project Alliance Agreement and the obligations and liabilities of a Non Owner Participant under the Project Alliance Agreement.

(c)  The Project Proposal must, as a minimum, incorporate the information, details and documentation set out in Schedule 4.

(d)  At any time prior to the Submission Date, the Project Owner may advise the Proponent in writing of any additional documents or further information that the Project Owner reasonably requires to be incorporated into the Project Proposal and the Proponent must incorporate the additional documents or further information into the Project Proposal.

(e)  Once the Project Proposal has been developed by the Proponent, the Proponent must submit the Project Proposal to the Project Owner for approval (or otherwise) in accordance with clause 7.1(f).

(f)  The Proponent must submit the Project Proposal to the Project Owner by no later than the Submission Date.