(a) If the Proponent is selected as the Successful Proponent and:
(1) the Project Owner requires amendments to the executed form of the Project Alliance Agreement provided by the Successful Proponent in its Project Proposal, to which the Successful Proponent agrees, the Successful Proponent and the Project Owner must execute the amended Project Alliance Agreement; and
(2) the Project Owner does not require any amendments to the executed form of the Project Alliance Agreement provided by the Successful Proponent in its Project Proposal, the Project Owner will execute that form of the Project Alliance Agreement,
within 10 Business Days of the date of notification by the Project Owner to the Proponent under clause 11.1(a)(5).
(b) The Proponent acknowledges that the Project Owner may select the Other Proponent as the Successful Proponent, and proceed to execution of a Project Alliance Agreement with the Other Proponent in accordance with its Alliance Development Agreement.