4.5.2  Survey structure

A structured questionnaire for self completion was developed, posing questions regarding:

•  Name and composition of alliance (Owner, designer, constructor and advisors).

•  Alliance agreement format (project vs. program alliance, and single vs. multiple TOC.

•  Perceived alliance performance based on reported project outcomes of time, cost, quality of work, functionality, safety, environment, community, other stakeholders, team dynamics, KRA achievement, and flexibility of approach.

•  TOC comparison (initial, final and actual).

•  Project duration comparison (initial, final and actual).

•  Activities undertaken prior to selecting an alliance.

•  Successful outcome indicators.

•  The possibility of using an alternative delivery method.

•  The use of cost criteria in the evaluation.

The questionnaire is included in the full Phase 1 Survey Results in Appendix A.