|
5. What format did the Alliance Agreement take? Note: • Project Alliance - means a project that is implemented as an Alliance - similar to - refer to Victorian Government Alliancing Practitioner's Guide; • Program Alliance - means a series of Project Alliances carried out by the same Alliance team |
|||||||||||||
|
|
Single TOC |
Multiple TOC |
|||||||||||
|
Project Alliance |
|
|
|||||||||||
|
Program Alliance |
|
|
|||||||||||
|
Other ie. ECI |
|
|
|||||||||||
|
If Other (please specify) |
|||||||||||||
|
|
|
|
|
|
|||||||||
|
6. How would you rate the Alliance's performance in the following areas (performance as set out in the accepted PAA - TOC): |
|||||||||||||
|
|
Poor |
Below |
Met |
Above |
Game Breaking |
||||||||
|
Time |
|
|
|
|
|
||||||||
|
Cost |
|
|
|
|
|
||||||||
|
Quality for Work |
|
|
|
|
|
||||||||
|
Functionality |
|
|
|
|
|
||||||||
|
Safety |
|
|
|
|
|
||||||||
|
Environment |
|
|
|
|
|
||||||||
|
Community |
|
|
|
|
|
||||||||
|
Other Stakeholders |
|
|
|
|
|
||||||||
|
Team Dynamics |
|
|
|
|
|
||||||||
|
KRA Achievement |
|
|
|
|
|
||||||||
|
Flexibility of Approach |
|
|
|
|
|
||||||||
|
7. Please answer the following questions: Note: • Initial Target Outturn Cost - means Target Cost Estimate (TCE) plus Fee; • Final Target Outturn Cost - means Final agreed TCE plus Fee adjusted for approved variations; • Actual Outturn Cost - means Total agreed Actual Cost plus Fee (excluding pain/gain share); • Target Cost Estimate (TCE) - means Direct Project Costs plus Project specific Overheads; • Fee - means Corporate Overheads and charges and Profit |
|||||||||||||
|
What was the initial target outturn cost ($m)? |
|
|
|||||||||||
|
|
|||||||||||||
|
What was the final target outturn cost ($m)? |
|
|
|||||||||||
|
|
|||||||||||||
|
What was the actual target outturn cost ($m)? |
|
|
|||||||||||
|
|
|||||||||||||
|
8. Please answer the following questions: Note: • Initial Project Duration - means the project durations as agreed in the TCE; • Final Project Duration - means the project duration as agreed and amended in terms of the Alliance Agreement; • Actual Project Duration - means the Actual project duration to complete the project in terms of the Alliance Agreement |
|||||||||||||
|
|
|||||||||||||
|
What was the initial Project duration? [months] |
|
|
|||||||||||
|
|
|||||||||||||
|
What was the final Project duration? [months] |
|
|
|||||||||||
|
|
|||||||||||||
|
What was the actual Project duration? [months] |
|
|
|||||||||||
|
|
|||||||||||||
|
9. Rate the items below in terms of their importance in delivery a successful outcome for this Alliance. Note: Please rate items on a scale of 1 to 7 with 1 being of highest importance and 7 being of lowest importance. |
|||||||||||||
|
Time |
|
|
|||||||||||
|
|
|
|
|||||||||||
|
Cost |
|
|
|||||||||||
|
|
|
|
|||||||||||
|
Flexibility of Approach |
|
|
|||||||||||
|
|
|
|
|||||||||||
|
Community |
|
|
|||||||||||
|
|
|
|
|||||||||||
|
Other Stakeholders |
|
|
|||||||||||
|
|
|
|
|||||||||||
|
Team Dynamics |
|
|
|||||||||||
|
|
|
|
|||||||||||
|
Certainty of Outcome |
|
|
|||||||||||
|
|
|
|
|||||||||||