1.7  Interpretation for Separable Portions

If the Project Owner makes a determination under clause 6.9 for any part of the Works to be divided into Separable Portions, the interpretation of:

(a)  "Certificate of Practical Completion";

(b)  "Date for Practical Completion";

(c)  "Date of Practical Completion"; and

(d)  "Practical Completion",

will apply separately to each Separable Portion and, where appropriate, references to the "Works" will mean so much of the Works as is comprised in the relevant Separable Portion.