In designing the Works under this Agreement, the Participants must ensure that the design for the Works:
(a) is consistent with the Project Proposal (including the Design Development Report);
(b) is such that, when constructed, the Works will be fit for the purpose and of the quality and standard of work that is stated in the Scope of Works;
(c) is constructible having regard to usual industry practices;
(d) makes the optimum use of the time available contemplated by this Agreement to complete the Works;
(e) can be constructed within the TOC and in accordance with the Project Owner's VFM Statement and the Alliance Objectives; and
(f) produces a minimum whole of life cost for the Works having regard to the requirements of the Project Owner's VFM Statement and the various design lives of each component of the Works and the requirements of the Scope of Works.