10.2  Issue of Certificate of Practical Completion

(a)  By no later than 20 Business Days from the date the ALT anticipates that Practical Completion will be reached, the ALT must notify the Project Owner of the date when Practical Completion is anticipated to be reached.

(b)  As soon as the ALT decides that Practical Completion has been reached, it must notify the Project Owner of the date when Practical Completion was reached.

(c)  The Project Owner must, if it agrees that Practical Completion has been reached, within 20 Business Days after receiving the notification of Practical Completion from the ALT, issue a certificate of Practical Completion (Certificate of Practical Completion) to the Participants, stating the Date of Practical Completion notified by the ALT.