11.3  Payments under Final Certificate

If the Project Owner and the NOPs agree with the contents of the Final Certificate, the Project Owner or NOPs (as the case may be) must make the payments contemplated by the Final Certificate within 20 Business Days of the date that the Final Certificate is received by the Project Owner.