(a) If the Project Owner does not agree with the contents of the Final Certificate, it must, within 20 Business Days after receiving the Final Certificate, notify the ALT which part of the contents of the Final Certificate it does not agree with and the reasons it does not agree.
(b) The ALT must then ensure that the Participants promptly address the matters specified by the Project Owner and when those matters have been addressed, re-submit the Final Certificate to the Project Owner.
(c) The Project Owner must then re-consider whether it agrees with the contents of the Final Certificate. If the Project Owner agrees with the contents of the Final Certificate then clause 11.3 will apply. If the Project Owner does not agree with the contents of the Final Certificate clause 11.4(a) will apply.