(a) The Participants acknowledge and agree that an industrial relations management plan in relation to the Works and the Project has been included in the Project Management System that is in compliance with relevant Statutory Requirements, codes of practice and guidelines (including the Code and the Guidelines, the Victorian Code and the Industrial Relations Principles). The Participants must implement and comply with the industrial relations management plan included as part of the Project Management System in performing the Works.
Guidance Note - Please note that where the Project Owner is using the Agreement for a Project in a jurisdiction other than Victoria, the Project Owner will need to review and amend this provision to reflect the relevant jurisdiction's requirements. |
(b) The NOPs acknowledge and agree that they must ensure that any Subcontractors engaged in respect of the performance of the Works under this Agreement will be accredited under the Australian Government Building and Construction OHS Accreditation Scheme established by section 35 of the Building and Construction Industry Improvement Act 2005 (Cth), at all times those Subcontractors are performing the Works under this Agreement.