(a) Subject to clause 17.4(b) and clause 29.15, any Participant or its nominated auditor may inspect and audit documentation referred to in clause 17.2:
(1) at the times identified in the audit plan to be developed by the Participants promptly after the date of this Agreement and approved by the ALT; or
(2) at any other time as agreed by the ALT.
(b) The Project Owner or its nominated auditor may inspect and audit any records or documentation:
(1) referred to in clause 17.2; and
(2) otherwise required to be made available to the Project Owner under clause 4.4,
at any time determined by the Project Owner.
(c) A Participant must provide each other Participant with proper access to their personnel and facilities to enable any Participant or its nominated auditor to undertake any inspection and audit of the kind set out in this clause 17.4.
(d) Subject to clause 17.4(e), all inspection and audit costs must be paid by the Participant undertaking the inspection and audit and are not Reimbursable Costs.
(e) If an inspection and audit under this clause reveals that the other Participant is in Default (as that term is defined in clause 24.1), then without limiting any other rights and obligations of a Participant, the Participant in Default is responsible for all costs incurred by the Participant undertaking the inspection and audit and those costs are not Reimbursable Costs.