22.2  Suspension by the Project Owner

Without limiting clause 22.5, if the Project Owner thinks that suspension of the whole or part of the Works is necessary or appropriate for any reason, the Project Owner may direct the Participants in writing to immediately suspend the progress of the whole or part of the Works for the period specified by the Project Owner in writing, and the Participants must promptly suspend the Works.