22.4  Recommencement

When the Project Owner becomes aware that the reason for suspension no longer exists, the Project Owner must direct the Participants to recommence the whole or the relevant part of the Works and the Participants must recommence the Works at the time directed by the Project Owner or, if no time is stated, within a reasonable time after the direction.