(a) If the Project Owner elects to terminate this Agreement under clause 23.1, subject to the Project Owner's rights under or in connection with this Agreement, the Project Owner must pay the NOPs, or the NOPs must pay the Project Owner (as the case may be), an amount calculated or decided under Schedule 12. The Participants must take all reasonable steps to minimise and mitigate any costs incurred by them arising from termination of this Agreement under clause 23.1.
(b) Upon payment of any termination payment by the Project Owner to the NOPs or the NOPs to the Project Owner (as the case may be) under this clause 23.2, the Project Owner and the NOPs must enter into a deed of release under which, subject to clause 29.17 which survives termination of this Agreement, each of the Project Owner and the NOPs:
(1) agree that all payments required to be made by the Project Owner or by the NOPs (as the case may be) in respect of this Agreement have been made in full; and