25.3  Works continuation

Without limiting any other rights of the Participants under this Agreement, if this Agreement is terminated for any reason whatsoever, the NOPs acknowledge and agree that the Project Owner is free to continue with the Works either:

(a)  with entirely new contractors and consultants; or

(b)  on an alliance, conventional contractual or any other basis that the Project Owner may decide, and the NOPs must do all things and execute all further documents necessary to ensure that the Project Owner is free to continue with the Works in the manner set out in this clause 25.3 within the time period prescribed by the Project Owner.