7  Site establishment costs

Costs associated with the establishment of each Site, including:

(a)  mobilisation and demobilisation;

(b)  connection and disconnection of temporary services;

(c)  the costs associated with negotiating, investigating, surveying and designing land acquisitions and arranging Site access, possession and laydown areas;

(d)  Site fencing, remedial fencing, access gates and hoardings;

(e)  protection of existing facilities;

(f)  Project signboard; and

(g)  inductions (to the extent not covered under clause 1 of this Schedule).