Guidance Note - Please note that some or all of these Reimbursable Costs may be bid by the NOPs as part of their Proposal and therefore the Project Owner needs to consider whether they are to be fixed as part of the setting of the TOC under the Alliance Development Agreement. |
The cost of:
(a) cabling;
(b) switching infrastructure;
(c) telephone system;
(d) implementation and installation;
(e) servers;
(f) network costs;
(g) data link costs;
(h) PCs (including design software and other software purchased specifically for the Works but excluding design software and software used by the Participants in their day to day operations);
(i) amortisations and licences;
(j) printers, plotters, MFM, scanners;
(k) cameras and videos to the extent they are purchased or used solely for the Works;
(l) MIS services and support charges; and
(m) IT support,
located at the Project Office.