(a) As soon as practicable after the Date of Practical Completion:
(1) the ALT will calculate the Interim Gainshare Amount or Interim Painshare Amount (if any and as the case may be) following determination of:
(A) the sum of the AOC in performing the Works to reach Practical Completion;
(B) the ALT's expectation of the AOC to the Final Completion Date; and
(C) the performance of the Participants against the KRAs and the Performance Modifiers for the period from date of this Agreement until the Date of Practical Completion; and
(2) subject to clauses 4(c)(1) and 4(c)(2) of this Schedule, the Project Owner will make a payment (if any) to the NOPs or the NOPs will make a payment (if any) to the Project Owner (as the case may be) in accordance with clause 3(c) of Schedule 8.
(b) As soon as practicable after the Final Completion Date:
(1) the ALT will calculate the Gainshare Amount or Painshare Amount (if any and as the case may be) following determination of:
(A) the sum of the AOC in performing the Works to the Final Completion Date; and
(B) the performance of the Participants against the KRAs and the Performance Modifiers for the period from the date of this Agreement until the Final Completion Date; and
(2) subject to clauses 4(c)(1) and 4(c)(2) of this Schedule, the Project Owner will make a payment (if any) to the NOPs or the NOPs will make a payment (if any) to the Project Owner (as the case may be) in accordance with clause 3(d) of Schedule 8.
[Alternative 2 - End]