KF 1: Defining the project's VfM proposition
Business cases often did not clearly define the project VfM proposition to the rigour required for investment decision making.
Particular findings:
■ Average increase from business case cost estimate to AOC was of the order of 45-55%.
■ Business case assessment of an optimum delivery method often tended to 'default' to alliancing using a non-price selection approach for NOPs and did not consider a range of other delivery options.
■ In general, a robust program and budget was not evident from the business case stage.