■ Procurement strategy should be selected on the basis of the project characteristics.
■ The selection of the alliance delivery method to attract scarce resources or to start the project earlier may not be appropriate if the associated price premium is considered. This premium may be acceptable if the risk profile of the project is high, however, for lower risk projects the premium may be excessive.