The key dates relating to the Selection Process are presented in the table below. The dates are subject to change and are provided as indicative dates only.
Stage | Event | Date |
|
| |
Phase 6 | Advertise Request for Proposals | [insert] |
Phase 7 | Interact with Proponents (workshops, etc) | [insert] |
Phase 8 | Closing Date for submission of Initial Proposal | [insert] |
Phase 9 | Commence evaluation of Initial Proposals | [insert] |
Phase 10 | Announcement of two Shortlisted Proponents | [insert] |
Phase 11 | Commence interactive development process (e.g. workshops) with Shortlisted Proponents | [insert] |
Phase 12 | Commence Financial Establishment Audit | [insert] |
Phase 13 | Commercial Alignment Workshop ([insert] days) | [insert] |
Phase 14 | Closing Date for submission of Project Proposals | [insert] |
Phase 15 | Commence evaluation of Project Proposals | [insert] |
Phase 16 | Selection of Successful Proponent by Project Owner | [insert] |
Execution of Project Alliance Agreement and commencement of works | ||
Phase 17 | Obtain [Board and] Ministerial approval to execute Project Alliance Agreement | [insert] |
Phase 18 | Execute Project Alliance Agreement | [insert] |
Phase 19 | Project commencement | [insert] |
Phase 20 | [insert] | |