6.2  RFP Phase Mandatory Criteria

The Proponent must, in its Initial Proposal, satisfy all the Mandatory Criteria set out in the table below. In the event that an Initial Proposal fails to satisfy the Mandatory Criteria, the Project Owner reserves the right, at its sole discretion, to:

(a)  elect not to further evaluate that Initial Proposal; or

(b)  proceed to complete its evaluation of that Initial Proposal.

The Evaluation Team may seek clarification from the Proponent or from any other source in order to assess whether or not a Proponent has satisfied the Mandatory Criteria.

Guidance Note: These criteria have been included for illustration purposes only. The Project Owner will need to determine the relevant Mandatory Criteria on a case-by-case basis and specify any documentation that may be required to support the Mandatory Criteria.

 

RFP Response Mandatory Criteria

Mandatory Criterion 1:

Past Experience

Demonstrate recent experience in design, construction, project implementation and construction management experience on at least one project similar to [insert nature of Project].

The following information is required:

(a)  project name and location;

(b)  details of the works, roles and responsibilities carried out;

(c)  the number and details of company employees engaged in carrying out the roles and responsibilities; and

(d)  client reference and contact details.

Mandatory Criterion 2:

Financial capacity

Demonstrate financial capacity to deliver the Project.

The following information is required from the Proponent:

(a) financial information for the last 3 years which includes:

i) copies of audited financial accounts for the past three financial years;

ii) details of any existing loan facilities, including terms and conditions, security provided and undrawn amounts;

iii) details of any financial constraints, including details of material commitments, covenants, or potential contingencies;

(b)  confirmation of capacity to provide a performance bank guarantee or performance bond if required by the Project Owner; and

(c)  if any Proponent is a subsidiary, confirmation of ability of that Member to provide a parent company guarantee, if required by the Project Owner.

Mandatory Criterion 3:

Safety

Demonstrate a suitable safety system to undertake the Project. Provide:

(a) evidence of Occupational Health and Safety Management System independently certified to [insert required certification level, e.g. AS 4801-2001 or National Safety Council of Australia Five Star certification (3, 4 or 5 stars only] or an approved equivalent independent standard of certification.

Mandatory Criterion 4:

Quality Management

Demonstrate a suitable quality management system to undertake the Project.

Mandatory Criterion 5:

Environmental Management

Demonstrate a suitable environmental management system to undertake the Project.

Mandatory Criterion 6:

Lodgement of Initial Proposal Form

Provide a completed and compliant Lodgement of Initial Proposal Form for each Member of the Proponent.