8.4 Specific TOC development probity considerations

The TOC development process during full price and partial price selection process allows the recommendation on the Preferred Proponent to be made based on a more comprehensive and direct evaluation of behaviours and capabilities demonstrated working on the actual project than compared to non-price selection. The structured observations made by the Owner's team(s) in the workshops and other interactions with the Proponents during the TOC Development Phase will be used by the Tender Evaluation Panel to make a recommendation to the Owner on the Preferred Proponent.

The Owner's Probity Advisor will tailor a specific probity plan to deal with selection challenges. The following section provides an overview of issues, however, it does not replace a well thought out and tailored probity plan.