Early Works

No early works were undertaken prior to the execution of the PAA.

On the other hand, due to the excellent relationship established by the Alliance with the two local authorities, a 'soft start' of preparation works was allowed before various (local authority) designations, outline plans and resource consents' had been signed and issued for the construction work.