No early works were undertaken prior to the execution of the PAA.
On the other hand, due to the excellent relationship established by the Alliance with the two local authorities, a 'soft start' of preparation works was allowed before various (local authority) designations, outline plans and resource consents' had been signed and issued for the construction work.