6.  RISK ALLOWANCES

This section should address the following:

•  Provide a brief description of the risks identified in the Business Case and identify any differences with the risks accounted in the Project Proposal.

•  Provide a description of the proposed risk sharing arrangements between the Owner and the proposed alliance.

•  Identify any project-related expenditure to cover risks that was not included as part of the TOC

•  Confirm whether appropriate resources and capabilities are in place for the Owner and the Proponent during the development and establishment of the alliance as well as during the delivery of the project.