242.1107 Contract clause.

(b)  When using the clause at FAR 52.242-2, include the following instructions in the contract schedule-

(i)  Frequency and timing of reporting (normally five working days after each reporting period);

(ii)  Contract line items, exhibits, or exhibit line items requiring reports;

(iii)  Offices (with addressees/codes) where reports should be sent (always include the contracting office and contract administration office); and

(iv)  The following requirements for report content-

(A)  The problem, actual or potential, and its cause;

(B)  Items and quantities affected;

(C)  When the delinquency started or will start;

(D)  Actions taken to overcome the delinquency;

(E)  Estimated recovery date; and/or

(F)  Proposed schedule revision.