PGI 215.404-1 Proposal analysis techniques.

(a)  General.

(i)  The objective of proposal analysis is to ensure that the final agreed-to price is fair and reasonable. When the contracting officer needs information to determine price reasonableness and the offeror will not furnish that information, use the following sequence of steps to resolve the issue:

(A)  The contracting officer should make it clear what information is required and why it is needed to determine fair and reasonable prices, and should be flexible in requesting data and information in existing formats with appropriate explanations from the offeror.

(B)  If the offeror refuses to provide the data, the contracting officer should elevate the issue within the contracting activity.

(C)  Contracting activity management shall, with support from the contracting officer, discuss the issue with appropriate levels of the offeror's management.

(D)  If the offeror continues to refuse to provide the data, contracting activity management shall elevate the issue to the head of the contracting activity for a decision in accordance with FAR 15.403-3(a)(4).

(E)  The contracting officer shall document the contract file to describe-

(1)  The data requested and the contracting officer's need for that data;

(2)  Why there is currently no other alternative but to procure the item from this particular source; and

(3)  A written plan for avoiding this situation in the future (e.g., develop a second source by...; bring the procurement in house to the Government by...).

(F)  Consistent with the requirements at FAR 15.304 and 42.1502 and the DoD Guide to Collection and Use of Past Performance Information, Version 3, dated May 2003, the contracting officer shall provide input into the past performance system, noting the offeror's refusal to provide the requested information.

(ii)  In some cases, supplies or services that are not subject to TINA may require a cost analysis (see paragraph (b)(iv) of this section). This will occur when a price analysis is not sufficient for determining prices to be fair and reasonable. In such cases, the contracting officer should consider the need for a Defense Contract Audit Agency audit of the cost data.

(iii)  Particular attention should be paid to sole source commercial supplies or services. While the order of preference at FAR 15.402 must be followed, if the contracting officer cannot determine price reasonableness without obtaining information or cost data from the offeror, at a minimum, the contracting officer must obtain appropriate information on the prices at which the same or similar items have been sold previously (often previous sales information was the basis of the commercial item determination and must be requested during price analysis of the information or data provided by the offeror). If previous sales information is not sufficient to determine price reasonableness, the contracting officer must obtain "information other than cost or pricing data" and, if necessary, perform a cost analysis.

(b)  Price analysis.

(i)  Price analysis should generally be performed on supplies or services that are not subject to TINA. Available commercial sales, published catalogs or prices, etc., can sometimes be obtained through market research and can provide a basis for determining if the proposed prices are fair and reasonable.

(ii)  In some cases, commercial sales are not available and there is no other market information for determining fair and reasonable prices. This is especially true when buying supplies or services that have been determined to be commercial, but have only been "offered for sale" or purchased on a sole source basis with no prior commercial sales upon which to rely. In such cases, the contracting officer must require the offeror to submit whatever cost information is needed to determine price reasonableness.

(iii)  The following procedures shall be adhered to when executing the price analysis steps at FAR 15.404-1(b)(2):

(A)  When the contracting officer is relying on information obtained from sources other than the offeror, the contracting officer must obtain and document sufficient information to confirm that previous prices paid by the Government were based on a thorough price and/or cost analysis. For example, it would not be sufficient to use price(s) from a database paid by another contracting officer without understanding the type of analysis that was performed to determine the price(s), and without verifying that the quantities were similar for pricing purposes. This does not necessarily need to be another analysis, but there should be coordination with the other office that acknowledges an analysis was performed previously.

(B)  When purchasing sole source commercial items, the contracting officer must request non-Government sales data for quantities comparable to those in the solicitation. In addition, if there have not been any non-Government sales, "information other than cost or pricing data" shall be obtained and a price or cost analysis performed as required.

(iv)  When considering advice and assistance from others, the contracting officer must pay particular attention to supplies or services that are not subject to TINA because they are "of a type" customarily used by the general public or "similar to" the item being purchased. There must be a thorough analysis of-

(A)  The available price information for the similar-type item;

(B)  The changes required by the solicitation; and

(C)  The cost of modifying the base item.

(v)  In some cases, the contracting officer will have to obtain "information other than cost or pricing data" from the offeror because there is not sufficient information from other sources to determine if prices are fair and reasonable. The contracting officer must use business judgment to determine the level of information needed from the offeror, but must ensure that the information is sufficient for making a reasonableness determination. For example, the offeror may have significant sales of the item in comparable quantities to non- Government entities, and that may be all the information needed, once the sales information is appropriately verified. On the other hand, there may be no non-Government sales and the contracting officer may be required to obtain cost information, and should do so. The request for additional information shall be limited to only that needed to determine prices to be fair and reasonable. For example, assume the proposal is 40 percent purchase parts, 30 percent labor, and the balance indirect rates. Also assume that the Defense Contract Management Agency (DCMA) has a forward pricing rate agreement with the offeror. It may be sufficient to limit requests to historical purchase records and/or vendor quotes and the proposed labor hours. Based on this information and the forward pricing rates from DCMA, the contracting officer may be able to determine price reasonableness.

(c)  Cost analysis.

(i)  When the contracting officer cannot obtain sufficient information to perform a price analysis in accordance with the pricing steps in FAR 15.404-1(b), a cost analysis is required.

(ii)  When a solicitation is not subject to TINA and a cost analysis is required, the contracting officer must clearly communicate to the offeror the cost information that will be needed to determine if the proposed price is fair and reasonable.

(iii)  To the extent possible, when cost or pricing data are not required to be submitted in accordance with Table 15-2 of FAR 15.408, the contracting officer should accept the cost data in a format consistent with the offeror's records.

(iv)  The contracting officer must always consider the need for field pricing support from the Defense Contract Management Agency, the Defense Contract Audit Agency, and/or other agencies.

(e)  Technical analysis.

Requesting technical assistance is particularly important when evaluating pricing related to items that are "similar to" items being purchased or commercial items that are "of a type" or require "minor modifications." Technical analysis can assist in pricing these types of items by identifying any differences between the item being acquired and the "similar to" item. In particular, the technical review can assist in evaluating the changes that are required to get from the "similar to" item, to the item being solicited, so the contracting officer can determine sufficient price/cost analysis techniques when evaluating that the price for the item being solicited is fair and reasonable.