Proper Use and Management of Cost-Reimbursement Contracts (FAR Case 2008-030)

Summary:

FAC 2005-50 includes an interim rule amending the Federal Acquisition Regulation (FAR) to implement section 864 of the Duncan Hunter National Defense Authorization Act for Fiscal Year 2009. This law aligns Page 14544 with the Presidential Memorandum on Government Contracting, issued on March 4, 2009, which directed agencies to save $40 billion in contracting annually by Fiscal Year (FY) 2011 and to reduce the use of high-risk contracts.

This rule provides regulatory guidance on the proper use and management of other than firm-fixed-price contracts (e.g., cost-reimbursement, time-and-material, and labor-hour).

Supplementary Information:

I. Background

This case implements section 864 of the Duncan Hunter National Defense Authorization Act for Fiscal Year 2009 (Pub. L. 110-417), enacted October 14, 2008. This law aligns with the President's goal of reducing high-risk contracting as denoted in the March 4, 2009, Presidential Memorandum on Government Contracting.

Section 864 requires the FAR to be revised to address the use and management of cost-reimbursement contracts and identifies the following three areas that the Defense Acquisition Regulation Council and the Civilian Agency Acquisition Council (Councils) should consider in amending the FAR--

a) Circumstances when cost-reimbursement contracts are appropriate;

b)  Acquisition plan findings to support the selection of a cost-reimbursement contract; and

c)  Acquisition resources necessary to award and manage a cost-reimbursement contract.

1.  Guidance on Cost-reimbursement contracts. As required, the Councils included additional coverage at FAR subpart 16.1, Selecting Contract Types, and at subpart 16.3, Cost-Reimbursement Contracts, to provide further guidance as to when, and under what circumstances, cost-eimbursement contracts are appropriate. Therefore, this rule makes the following changes:

 FAR 16.103, Negotiating contract type, is amended to revise paragraph (d) to reflect additional documentation when other than a firm-fixed-price contract type is selected.

 FAR 16.104, Factors in selecting contract types, is amended to add a new paragraph (e) to provide guidance to the contracting officer to consider combining contract types if the entire

 contract cannot be firm fixed-price.

 FAR 16.301-2, Application, is amended to provide guidance to the contracting officer as to the circumstances in which to use cost-reimbursement contracts as well as outlining the rationale for documentation for selecting this contract type.

 FAR 16.301-3, Limitations, is amended to (1) provide additional guidance to the contracting officer as to when a cost-reimbursement contract may be used, (2) ensure that all factors have been considered per FAR 16.104, and (3) ensure that adequate Government resources are available to award and manage this type of contract.

 FAR 7.104(e) also requires the designation of a properly trained contracting officer's representative (COR) (or contracting officer's technical representative (COTR)) prior to award of the contract or order.

2.  Identification of acquisition plan findings. FAR 7.103, Agency-head responsibilities, is amended and renumbered to add new paragraphs 7.103(d), 7.103(f), and 7.103(j) to ensure that acquisition planners document the file to support the selection of the contract type in accordance with FAR subpart 16.1; ensure that the statement of work is closely aligned with the performance outcomes and cost estimates; and obtain an approval and signature from the appropriate acquisition official at least one level above the contracting officer. FAR 7.105(b)(5)(iv) was added to discuss the strategy to transition from cost-reimbursement contracts to firm-fixed-price contracts. Although FAR 7.105(b)(5), Acquisition considerations, requires the acquisition plans to include a discussion of contract type selection and rationale, the Councils believe that a greater emphasis on the use of cost-reimbursement contracts should be added and included a new paragraph at FAR 7.105(b)(3), Contract type selection. Additionally, FAR 16.301-3(a) has been amended and renumbered.

3.  Acquisition workforce resources. The Councils recognize that assigning adequate and proper resources to support the solicitation, award, and administration of other than firm-fixed-price contracts (cost-reimbursement, time-and-material, and labor-hour) contract is challenging. There is also great concern that a lack of involvement in contract oversight by program offices is primarily present in other than firm-fixed-price contracts. Therefore, from the outset, contracting officers should be assured, to the greatest extent practicable, that the right resources in number, kind, and availability be assigned to support other than firm-fixed-price contracts. The Councils consider that greater accountability for the management and oversight of all contracts, especially other than firm-fixed-price contracts, can be gained and improved by requiring that properly trained CORs or COTRs (see FAR 2.101(b)(2), Definitions) be appointed before award. Therefore, FAR 7.104, General Procedures, and FAR 16.301-3(a)(4)(i) are amended to reflect that prior to award of a contract, especially on other than firm-fixed price contracts, at least one COR or COTR qualified in accordance with FAR 1.602-2 is designated. FAR 1.602-2, Responsibilities, is amended to add a new paragraph (d) outlining the requirement for the contracting officer to designate and authorize, in writing, a COR on contracts and orders, as appropriate. Additionally, a new section was added at FAR 1.604, Contracting officer's representative, outlining the COR's duties.

4.  Contract administration functions. A new paragraph was added at FAR 42.302(a)(12) to require that the contracting officer determine the continuing adequacy of the contractor's accounting system during the entire period of contract performance. Also, paragraph (a)(12) was added to the list of functions at FAR 42.302(a) that cannot be retained and that must be delegated by the contracting officer when delegating contract administration functions to a contract administration office in accordance with FAR 42.202(a).

Dates:

The Effective Date for this interim rule is 16 March 2011.

Interested parties should submit written comments to the Regulatory Secretariat on or before 16 May 2011 to be considered in the formulation of a final rule.

Click here to read the entire Federal Register notice for this rule.