Business Systems--Definition and Administration (DFARS Case 2009-D038)

Summary:

DCN 20120224 adopts as final, with changes, an interim rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to improve the effectiveness of DoD oversight of contractor business systems.

Supplementary Information:

I.  Background

DoD published an initial proposed rule for Business Systems--Definition and Administration (DFARS Case 2009-D038) in the Federal Register on January 15, 2010 (75 FR 2457). Based on the comments received, DoD published a second proposed rule on December 3, 2010 (75 FR 75550). The public comment period closed January 10, 2011.

On January 7, 2011, the National Defense Authorization Act (NDAA) for Fiscal Year (FY) 2011 was signed into law (Pub. L. 111-383). Section 893 of the NDAA for FY 2011, Contractor Business Systems, set forth statutory requirements for the improvement of contractor business systems to ensure that such systems provide timely, reliable information for the management of DoD programs. Based on the comments received in response to the second proposed rule and the requirements of the NDAA for FY 2011, DoD published an interim rule with request for comments on May 18, 2011 (76 FR 28856). The public comment period ended on July 18, 2011. Comments were received from 14 respondents in response to the interim rule.

Contractor business systems and internal controls are the first line of defense against waste, fraud, and abuse. Weak control systems increase the risk of unallowable and unreasonable costs on Government contracts. To improve the effectiveness of Defense Contract Management Agency (DCMA) and Defense Contract Audit Agency (DCAA) oversight of contractor business systems, DoD has clarified the definition and administration of contractor business systems as follows:

A.  Contractor business systems have been defined as accounting systems, estimating systems, purchasing systems, earned value management systems (EVMS), material management and accounting systems (MMAS), and property management systems.

B.  Compliance enforcement mechanisms have been implemented in the form of a business systems clause which includes payment withholding that allows contracting officers to withhold a percentage of payments, under certain conditions, when a contractor’s business system contains significant deficiencies. Payments could be withheld on--

 Interim payments under--

o  Cost-reimbursement contracts;

o  Incentive type contracts;

o  Time-and-materials contracts;

o  Labor-hour contracts;

 Progress payments; and

 Performance-based payments.

II. Discussion and Analysis

Analysis of the public comments is provided here.

Dates:

The Effective Date for this final rule is 24 February 2012.

Click here to read the entire Federal Register notice for this rule.