4.1301 Policy.
2. Amend section 4.1301 by adding paragraph (d) to read as follows:
4.1301 Policy.
* * * * *
(d)
(1) Agency procedures for the return of Personal Identity Verification (PIV) products shall ensure that Government contractors account for all forms of Government-provided identification issued to Government contractor employees under a contract, i.e., the PIV cards or other similar badges, and shall ensure that contractors return such identification to the issuing agency as soon as any of the following occurs, unless otherwise determined by the agency:
(i) When no longer needed for contract performance.
(ii) Upon completion of a contractor employee's employment.
(iii) Upon contract completion or termination.
(2) The contracting officer may delay final payment under a contract if the contractor fails to comply with these requirements.