3. Remedies for Violations by the Contractor
Comment: One respondent objected to inclusion of the list of remedies in the clause at FAR 52.203-16(d), stating that the FAR contains adequate remedies to address non-compliance with any material requirement of a contract, which includes the proposed FAR clause 52.203-16.
Response: While the list of remedies included within FAR 52.203-16 specifically identified those remedies available for violations involving potential conflicts, it was not intended to create new remedies. For this reason, the Councils have removed the paragraph regarding remedies from the clause. Removal of this section also addresses comments from several respondents related to individual remedies included in the list.
Comment: One respondent recommended adding a provision stating that certain violations should immediately be entered into the new Federal Awardee Performance and Integrity Information System (FAPIIS).
Response: Inclusion in the FAPIIS database is already adequately covered. For violations that result in suspension, debarment, or termination of the contract for default or cause, such actions will be entered into FAPIIS in accordance with the requirements published in the Federal Register at 75 FR 14059 on March 23, 2010. The other violations are of a type that would be entered in FAPIIS through the contracting officer performance evaluation of the contractor.