1. Cross References
Comment: One respondent stated that there is a contradiction between FAR 12.207 and proposed FAR 16.201, which states that the contracting officer shall use firm-fixed-price or fixed-price with economic price adjustment contracts when acquiring commercial items. The respondent recommended revising FAR 16.201 to reference FAR 12.207(b), which states the conditions for use of T&M or LH contracts to acquire commercial services, which are a subset of commercial items.
Response: A cross-reference to FAR 12.207(b) has been added at FAR 16.201, to reference the exception to the required use of fixed-price contracts for acquisition of commercial items.
Comment: A respondent noted that FAR 8.405-2(e)(2)(ii) would require the contracting officer to follow the competitive procedures at FAR 8.405-2(c), but, in contrast, FAR 12.207(b)(1)(i)(B) provides that procedures for other than full and open competition may be used if the agency receives at least two offers. The respondent believed that it would be consistent with the latter approach to give an agency the discretion to use other than the competitive procedures at FAR 8.405-2(c) if at least two quotes are received for the task order.
Response: FAR Case 2007-012, which was published in the Federal Register at 76 FR 14548 on March 16, 2011 (FAC 2005-50), provides an interim rule that sets forth the requirements for the use of limited sources and strengthens competition rules in FAR subpart 8.4. FAR 8.405-2(c) does not preclude the acquisition of commercial services under T&M and LH contracts on other than a competitive basis under 8.405-2(c)(3)(i), provided the procedures outlined in FAR 8.405-6 are followed. The references to FAR part 12 in the proposed rule will be deleted.
Comment: One respondent stated that, with regard to orders placed under the Federal Supply Schedule program and indefinite-delivery contracts, FAR 12.207(c)(2) references both FAR subparts 8.4 and 16.5, while FAR 12.207(c)(3) references only FAR subpart 16.5. The respondent recommended that, for the sake of clarity, either (a) only FAR 12.207 should include all guidance regarding T&M or LH orders or (b) guidance should be included in both FAR subparts 8.4 and 16.5.
Response: It is not necessary to cross-reference to FAR subpart 8.4 at FAR 12.207(c)(3) because the requirement for a determination and findings does not apply to individual orders when the basic contract allows only for T&M or LH orders, which is not the case for Federal Supply Schedule contracts.