4. Eliminate Distinctions Between Single-Award and Multiple-Award BPAs
Comment: One respondent stated that FAR 8.405-3(a) of the interim rule should be revised to place single-award BPAs on par with multiple-award BPAs. The respondent indicated that FAR 8.405-3 does not limit multiple-award BPAs to a one-year base and up to four one-year options, as required for single-award BPAs, nor does it require approval of the competition advocate to extend a multiple-award BPA. The respondent further stated the regulation should be revised to provide that the decision to use a single-award BPA versus a multiple-award BPA be documented and addressed in the acquisition plan for the BPA with the factors to be considered.
Response: The rule includes a preference for multiple-award BPAs, but does not prohibit the establishment of a single-award BPA. A single-award BPA is appropriate in certain circumstances. The multiple-award preference is intended to facilitate and enhance competition involving orders placed under FSS BPAs. The Councils concluded that the limit on the duration for single-award BPAs supports the preference for multiple-award BPAs and competition. However, the requirement for competition advocate approval at the annual review of a single-award BPA has been removed for the final rule. The contracting officer's determination whether to establish a single-award BPA or multiple-award BPAs must be documented in the file in accordance with FAR 8.405-3(a)(7).