8. Seeking Price Reduction Is Inconsistent With Competition
Comment: One respondent stated that the requirement that contracting officers seek a price reduction when placing an order over the SAT is inconsistent with the requirement that purchase orders over the SAT be competed. The FAR is built, in part, on the concept that competition drives a fair and reasonable price. As such, it is unclear, from the respondent's perspective, why contracting officers should be required to seek a further price reduction after a competitive procurement is awarded because the successful contractor has already provided its best price in order to win the procurement. The respondent argued that this requirement will likely result in contractors preparing their original price list in anticipation of multiple layers of price negotiation during the competitive procurement process and thereafter.
Response: Pursuant to the Government Accountability Office (GAO) report number GAO-09-792 entitled "Agencies are not Maximizing Opportunities for Competition or Savings Under BPAs Despite Significant Increase in Usage," requesting a price reduction is not inconsistent with competition. A contracting officer can meet this requirement at any time via a solicitation, or anytime thereafter. This rule does not require the contractor to reduce its prices when asked to do so by the Government.