I. Background
DoD published an interim rule at 75 FR 34942 on June 21, 2010, to amend DFARS parts 217 and 241 to authorize the Department of Defense to enter into a contract for a period not to exceed 10 years for the purchase of electricity from sources of renewable energy, as that term is defined in section 203(b)(2) of the Energy Policy Act of 2005 (42 U.S.C. 15852(b)(2)). Section 828 of the National Defense Authorization Act (NDAA) for Fiscal Year (FY) 2008 (Pub. L. 110-181) authorizes DoD to enter into a contract for a period in excess of five years only if the head of the contracting activity determined, on the basis of a business case analysis prepared by DoD, that--
(1) The proposed purchase of electricity under such contract is cost effective; and
(2) It would not be possible to purchase electricity from the source in an economical manner without the use of a contract for a period in excess of five years.