252.227-7037 Validation of restrictive markings on technical data.
13. Amend 252.227-7037 by--
(a) Amending the introductory text by removing "227.7102-3(c)" and adding in its place "227.7102-4(c)";
(b) Amending the clause date by removing "(SEP 1999)" and adding in its place "(SEP 2011)"; and
(c) Revising paragraphs (b), (c), (f), and (l) to read as follows:
252.227-7037 Validation of restrictive markings on technical data.
* * * * *
(b) Presumption regarding development exclusively at private expense.
(1) Commercial items. For commercially available off-the-shelf items (defined at 41 U.S.C. 104) in all cases, and for all other commercial items except as provided in paragraph (b)(2) of this clause, the Contracting Officer will presume that a Contractor's asserted use or release restrictions are justified on the basis that the item, component, or process was developed exclusively at private expense. The Contracting Officer shall not challenge such assertions unless the Contracting Officer has information that demonstrates that the item, component, or process was not developed exclusively at private expense.
(2) Major systems. The presumption of development exclusively at private expense does not apply to major systems or subsystems or components thereof, except for commercially available off-the-shelf items (which are governed by paragraph (b)(1) of this clause). When the Contracting Officer challenges an asserted restriction regarding technical data for a major system or a subsystem or component thereof on the basis that the item, component, or process was not developed exclusively at private expense, the Contracting Officer will sustain the challenge unless information provided by the Contractor or subcontractor demonstrates that the item, component, or process was developed exclusively at private expense.
(c) Justification. The Contractor or subcontractor at any tier is responsible for maintaining records sufficient to justify the validity of its markings that impose restrictions on the Government and others to use, duplicate, or disclose technical data delivered or required to be delivered under the contract or subcontract. Except as provided in paragraph (b)(1) of this clause, the Contractor or subcontractor shall be prepared to furnish to the Contracting Officer a written justification for such restrictive markings in response to a challenge under paragraph (e) of this clause.
* * * * *
(f) Final decision when Contractor or subcontractor fails to respond. Upon a failure of a Contractor or subcontractor to submit any response to the challenge notice the Contracting Officer will issue a final decision to the Contractor or subcontractor in accordance with paragraph (b) of this clause and the Disputes clause of this contract pertaining to the validity of the asserted restriction. This final decision shall be issued as soon as possible after the expiration of the time period of paragraph (e)(1)(ii) or (e)(2) of this clause.
Following issuance of the final decision, the Contracting Officer will comply with the procedures in paragraphs (g)(2)(ii) through (iv) of this clause.
* * * * *
(l) Flowdown. The Contractor or subcontractor agrees to insert this clause in contractual instruments with its subcontractors or suppliers at any tier requiring the delivery of technical data.
* * * * *