C. Flow Down of Provision to Subcontractors
Comment: A respondent stated that the interim rule (published as DFARS subpart 212.71) fails to clearly address the common situation in which a nontraditional defense contractor may simultaneously be a subcontractor or supplier to a traditional defense contractor. The respondent recommended the new DFARS rule make clear that it may and should flow down through any prime contract, to the suppliers/subcontractors.
Response: Unlike certain clauses, provisions are not flowed down to subcontractors. Solicitation provisions are to be completed and submitted by the prospective prime contractor with its offer. Furthermore, it is irrelevant to the program if a nontraditional defense contractor is simultaneously a subcontractor or supplier to a traditional defense contractor. As previously stated, section 866 only covers award to a prime contractor. No changes have been made to the final rule as a result of this comment.