9. DoD Officials' Remediation Responsibility
Comment: A number of respondents stated that the interim rule does not address DoD officials working with the contractor to remediate deficiencies or to develop a corrective action plan. The NDAA for FY 2011 contains the requirement for DoD officials to work with the contractor to correct cited deficiencies. The respondents suggested that this language be explicitly stated in the final rule along with additional language that would promote a "team effort" resolution of any significant deficiency. Further, the respondents suggested that the Government should be required to consider mitigating controls as part of any evaluation as to the reliability of information produced by a business system(s).
Response: The language in the rule complies with the NDAA for FY 2011. The rule identifies cognizant contracting officers as the DoD officials who are available to work with contractors in the process of identifying significant deficiencies, accepting corrective action plans, and monitoring the contractor's progress in correcting the deficiencies. Contracting officers will notify the contractor, in writing, providing a description of each significant deficiency in sufficient detail to allow the contractor to understand the deficiency, and then identify any issues with a contractor's corrective action plan.