3.11.3 Most Probable Cost (MPC)
When Section M identifies that the Cost/Price Factor will involve Government estimation of a MPC, Section L instructions must require offerors to provide both their proposed cost/price as well as their individual analysis of cost/price estimating uncertainty for ACAT I programs and other programs using MPC. RFPs should direct offerors to refer to or actually provide a copy of the Air Force Cost and Risk Uncertainty Handbook, located on the FM Knowledge Now Website at https://afkm.wpafb.af.mil/afcruh. Offerors will be instructed to provide both their proposed cost/price and their analysis of uncertainty as part of the cost/price proposal volume.
Note: ACAT SDD programs that use a Cost-Reimbursement or Fixed-Price Incentive type contract must perform a cost/price risk evaluation, which includes Government estimation of a MPC. The cost/price volume, Section L instructions should address the cost/price risk rating evaluation.