PRICE

PRICE

Relevancy Rating

Equally relevant to sensor and software contracts


(Note that this is the only area considering performance over more than the past 3/5 years)

Very Relevant

>$75 M;

> 3 Yr. effort duration

Relevant

Either < $75 M or < 3 Yr. effort duration

Somewhat Relevant

Either < $1 M or < 2 Yr. effort duration

Not Relevant

 No contracts experience

Performance Guidance

Exceptional = Blue

Under cost (not counting government directed cost growth)

Satisfactory = Green

At cost (not counting government directed cost growth)

Marginal = Yellow

Up to 20% over cost (not counting government directed cost growth)

Unsatisfactory = Red

More than 20% over cost (not counting government directed cost growth)

Additional Cost performance considerations:

Ability to anticipate, identify, and control cost growth.

Ability to use a validated cost/schedule control system

Submit accurate and timely financial reports and credible forecasts of future program costs.