(iii) Step Three: Verify That Your CLIN Structure Accurately Reflects Requirements And Funding Constraints.
Obtain a copy of the latest version of the program's Exhibit MYP-3, Contract Funding Plan. Verify that the copy you have accurately reflects the program's official requirements and funding expectations. This Contract Funding Plan is supposed to reflect:
(A) the quantity of end items required in each year;
(B) the years in which advance procurement is to be performed; and
(C) the end items that are to benefit from the advance procurement effort.
Your CLIN structure should reflect the same things.