III.  Acquisition Milestones

Include the following: (add additional milestones that may apply and/or exclude those that do not apply to this particular acquisition):

 Acquisition plan approval

 Approval of J&A for other than full and open competition (if necessary)

 Issuance of synopsis

 Request solicitation review (local review, JA review, HQ review/approval)

 Completion of solicitation review/Issue solicitation

 Conduct pre-proposal conference

 Receipt of past performance information/Receipt of proposals

 Begin evaluation of past performance information

 Complete evaluation of past performance information

 Request audit and field pricing support (if necessary)

 Complete discussions if competitive acquisition

 Prepare PPNM if non-competitive acquisition

 Request contract clearance (local review, JA review, HQ review/approval)

 Receive contract clearance /Request Final Proposal Revisions if competitive acquisition

 Receive Final Proposal Revisions if competitive acquisition

 Begin negotiations if non-competitive acquisition

 Complete negotiations if non-competitive acquisition

 Complete FPNM if non-competitive acquisition

 Debriefing prepared

 Contract award

 Conduct debriefings

 Hold pre-preconstruction conference

 Contract start date/contract completion date